Client Approvals

The Custom Home Selections Checklist: Every Decision Your Client Needs to Make (and When)

By Ally team6 min read

The Custom Home Selections Checklist: Every Decision Your Client Needs to Make (and When)

Summary

Custom home selections should be scheduled, not left open-ended. This checklist lists every common owner decision by build phase, from preconstruction through finishes, with the latest point each one can be made without delaying construction, based on typical lead times.

On this page
  1. Key takeaways
  2. How to use this checklist
  3. Phase 1: Preconstruction and design
  4. Phase 2: Framing and dry-in
  5. Phase 3: Rough-ins (plumbing, electrical, mechanical, low voltage)
  6. Phase 4: Insulation, drywall and interior finishes
  7. Phase 5: Final finishes and closeout
  8. Common selection traps
  9. How to run selections meetings that end in decisions
  10. How Ally keeps selections on schedule
  11. Frequently asked questions

A custom home selections checklist lists every decision the homeowner must make, organized by build phase, with the latest date each can be made without delaying the schedule. The rule of thumb: a selection is due when the material must be ordered, which is its install date minus the supplier’s lead time and an ordering buffer. Long-lead items like windows and cabinetry are due months before anyone installs them.

Key takeaways

  • Schedule selections backward from install dates and lead times, not forward from “when the client is ready.”
  • Many decisions are due far earlier than homeowners expect: windows, cabinetry, plumbing rough-in valves and electrical layout come before drywall.
  • Rough-in decisions (fixture locations, valve types, lighting and low-voltage layout) lock in long before finishes are chosen.
  • Give every selection an owner and a decide-by date, and track approvals in one place the owner, architect and contractor all see.

How to use this checklist

Treat the timing below as a starting point. Lead times vary by market, supplier and season, and custom or imported products can take much longer. For each item on your project:

  1. Find the install or rough-in date on your construction schedule.
  2. Confirm the current lead time with the supplier.
  3. Subtract the lead time plus one to two weeks of ordering and submittal buffer.
  4. That is the latest decision date. Put it on the selections list with an owner.

The “latest decision point” column below describes when a decision is typically needed relative to construction milestones, assuming common lead times.

Phase 1: Preconstruction and design

SelectionLatest decision pointNotes
Contract type, allowances and budget targetsBefore contract signingAgree which items are allowances and how overages work. See allowances explained.
Foundation type, basement scope, slab vs. crawlspaceBefore permit drawingsDrives structure and permitting.
Window and exterior door manufacturer, style, colorBefore framing startsRough openings depend on unit sizes; lead times are often 8–16+ weeks.
Roofing materialBefore framingAffects structural loads and roof framing details.
Fireplace type and fuel (gas, wood, electric)Before framingVenting, chase framing and gas line routing.
HVAC system type and zoningBefore framingMechanical room size, chases, duct routing.
Elevator, lift or dumbwaiterBefore foundationPit and shaft dimensions; long lead times.
Solar, generator, battery storageBefore framingElectrical service size, conduit and roof layout.

Phase 2: Framing and dry-in

SelectionLatest decision pointNotes
Exterior siding, stone and trim materials4–8 weeks before exterior finishesStone and specialty cladding can run long.
Garage doors6–8 weeks before installationOpenings are framed earlier; confirm sizes before framing.
Built-in cabinetry and millwork designBefore rough-in (shop drawings need final dimensions)Custom cabinetry commonly needs 10–16 weeks after shop drawing approval.
Shower configurations (curbless, steam, bench, niches)Before framing is completeFloor recesses, blocking and steam venting are framed in.
Wall-mounted TVs, art lighting, heavy fixturesBefore framing inspectionBlocking locations.
Stair design, railings and treadsBefore framing (structure); 6–10 weeks before install (finish)Custom metal or glass railings run long.

Phase 3: Rough-ins (plumbing, electrical, mechanical, low voltage)

This is the phase homeowners most often underestimate. Locations and valve types are locked in before drywall, even if the finish fixtures are chosen later.

SelectionLatest decision pointNotes
Plumbing fixture types and locations (wall-mount vs. deck-mount faucets, tub filler, shower system)Before plumbing rough-inRough-in valves are fixture-specific.
Water heater type (tank, tankless, recirculation)Before plumbing rough-inVenting, gas and electrical needs.
Kitchen appliance modelsBefore rough-in and cabinet shop drawingsCutouts, gas, electrical and venting are model-specific.
Lighting plan: recessed, pendants, sconces, under-cabinetBefore electrical rough-inBox locations and circuits. Finish fixtures can follow.
Switch and outlet locations, dimming, smart controlsBefore electrical rough-in walkthroughDo a homeowner walkthrough with the electrician.
Low-voltage: Wi-Fi, audio, security, cameras, shadesBefore low-voltage rough-inMotorized shade pockets and wiring are framed and wired early.
Central vacuum, intercom, pet doorsBefore rough-inEasy to forget, hard to add later.

Phase 4: Insulation, drywall and interior finishes

SelectionLatest decision pointNotes
Drywall finish level, ceiling treatments, wall panelingBefore drywallLevel 5 finish and plaster change cost and duration.
Interior doors and door hardware6–10 weeks before trimCustom doors and hardware can run 10+ weeks.
Trim and casing profiles4–6 weeks before trimCustom profiles need knife grinding.
Flooring: hardwood, stone, tile6–12 weeks before installationWood needs acclimation time on site.
Tile for baths, kitchen backsplash, laundry6–10 weeks before tile startsImported or handmade tile often longer.
Countertops: material and slab selectionBefore cabinet install (template after install)Visit the slab yard early; fabrication follows template.
Cabinet finishes and hardwareWith cabinet orderFinish samples should be approved in writing.

Phase 5: Final finishes and closeout

SelectionLatest decision pointNotes
Paint and stain colors2–3 weeks before paintingApprove on site with samples under real light.
Decorative light fixtures6–10 weeks before trim-outImported fixtures can run longer.
Plumbing trim and finish fixtures6–8 weeks before trim-outRough valves already set the family.
Mirrors, shower glass, closet systemsAfter tile and paint (field measure)Field measured; 3–6 weeks to fabricate.
Window treatments4–8 weeks before move-inMotorized shade wiring was set at rough-in.
Landscape, hardscape, exterior lightingBefore final gradingIrrigation and lighting sleeves go in earlier.

Common selection traps

  • Appliances chosen after cabinets are ordered. Panel-ready and professional appliances change cabinet dimensions. Lock models before shop drawings.
  • “We’ll pick fixtures later.” True for the finish trim, not for the rough-in valve or wall-mount spout heights.
  • Unapproved samples. A finish sample the owner “liked” in a meeting isn’t an approval. Record the approved sample, version and price.
  • Allowance surprises. Show the running allowance balance as selections are made, not at the end.

How to run selections meetings that end in decisions

A checklist only works if decisions actually get made. Most builders run a series of selections meetings, grouped so related choices happen together: exterior materials and windows in one session, kitchen and baths in another, lighting and electrical layout with the electrician on site.

  • Send the agenda and options in advance. The homeowner should arrive having seen the two or three options for each item, with prices and lead times.
  • Invite the right people. Bring the interior designer for finishes, the architect when a decision affects the drawings, and the relevant trade for layout walkthroughs.
  • Separate “we like this” from “approved.” End each item with one of three outcomes: approved to proceed, approved to price, or still open with an owner and a date.
  • Confirm in writing the same day. Send the decisions, prices and schedule impact for approval through your normal process, and update the allowance balances.

Open items carry forward to the next meeting or your regular owner–architect–contractor meeting until they are closed.

How Ally keeps selections on schedule

Ally tracks every selection and approval in one place the owner, architect and contractor can all see. Selection requests go to the homeowner with photos and details; they can ask questions and approve digitally, and Ally follows up automatically on pending approvals. Every approval is timestamped and searchable, and approved changes flow into the budget and schedule, so everyone stays organized, informed and aligned on budget, schedule and decisions.

Explore client approvals in Ally, and see how to keep homeowner selections moving for the process behind this checklist.

Frequently asked questions

When do you choose finishes when building a custom house?

Earlier than most homeowners expect. Structural and layout decisions come before framing, rough-in decisions (fixture locations, valves, lighting layout, low voltage) before drywall, and most finish materials 6–12 weeks before installation. Work backward from each item’s install date and lead time.

What should be on a new construction selections list?

Everything the homeowner must decide: windows and doors, exterior materials, roofing, cabinetry and millwork, appliances, plumbing and lighting fixtures, electrical and low-voltage layout, flooring, tile, countertops, hardware, paint, mirrors, closets, window treatments and landscape. Group them by build phase with a decide-by date for each.

How far in advance do custom home selections need to be made?

It depends on lead time. Windows and custom cabinetry often need decisions two to four months before installation; tile, flooring and lighting six to twelve weeks; paint two to three weeks. Always confirm current lead times with suppliers, which vary by market and season.

Who should manage the selections schedule on a custom home?

The contractor usually owns the overall schedule and the decide-by dates, often with the interior designer or architect presenting options. What matters is that each selection has one named owner responsible for getting the decision made and that everyone works from the same list.

Want a selections process your whole team can see? Book a demo.

Get started with Ally

Start with one project and expand as your business grows. No hidden fees, no long-term contracts.

30-day money back guaranteeNo lock-in contracts